Reg 851 section 7 requires a pre-start health and safety review before new or modified equipment, structures or processes are used in an Ontario factory, when one of eight Table items applies and no exemption covers it. The eight items cover flammable liquids, machine safeguarding, racks, ignition risks, dust collectors, foundries, lifting devices and ventilation.

Most plants first run into Reg 851 section 7 at the purchase order stage: a robot cell with a light curtain, a taller pallet rack, a jib crane bolted to a building column. The current text dates from January 1, 2022, when O. Reg. 434/21 rewrote the triggers and the Table, so summaries written before then often get the exemptions wrong. An Ontario engineer signs the report for Items 1 to 7; Item 8 can go to a professional engineer or another qualified person, such as a certified industrial hygienist. Below, each Table row gets a short section and a link to the page that covers it in depth.

What Reg 851 section 7 says

Section 7 of O. Reg. 851, Industrial Establishments puts the duty on the owner, lessee or employer. A pre-start review is required in a factory when an applicable provision applies and a matching circumstance from the Table will exist, for either of two reasons.

  1. Something new is coming: a new apparatus, structure or protective element is to be built, added or installed, or a new process is to be used.
  2. Something existing is changing: an apparatus, structure, protective element or process is to be modified, and staying compliant needs new or modified engineering controls, other new or modified measures, or a mix of both.

The current text came from O. Reg. 434/21, which replaced the trigger, the report rules and the Table and has been in force since January 1, 2022. It also revoked the old subsections 10 to 15. Older summaries that mention a general exemption for previously reviewed or listed equipment describe rules that no longer exist. That matters most for second-hand machinery moving into a new plant, which gets no credit for a seller's old review.

Two limits frame everything else. Section 7 applies only in a factory as the Occupational Health and Safety Act defines it, which takes in manufacturing, assembly, repair work and warehouses that use machinery. It doesn't apply at a logging operation. Within a factory, routine maintenance with identical parts and moving equipment within the same workplace without triggering changes fall outside the section altogether.

The eight items in the Table

Each row of the Table names a circumstance, the sections of Reg. 851 the review must address, and any exemption. Here's the short version before the detail.

Table to section 7 of O. Reg. 851, summarized
ItemCircumstanceExemption in the Table
1More than 235 L of flammable liquids in a building or room, or any dispensingStorage in adequate cabinets only (235 L per cabinet, groups of three, 30 m apart); none for dispensing
2Stop-signal safeguarding devices or interlocked barrier guards used as protective elementsMachine and element made and installed to current applicable standards
3Loads stored on a rack or stacking structureRack designed and tested to current applicable standards
4A process with a risk of ignition or explosionProcess inside a spray booth made and installed to current applicable standards
5A dust collector with a risk of ignition or explosionNone
6Aluminum or steel production, or a foundryNone
7A crane or other structure-supported lifting device, or a vehicle lift or hoistStructure originally designed for the device; certified vehicle lift
8Ventilation used to keep a hazardous agent below Reg. 833 limitsPortable extractor that doesn't exhaust outdoors

Item 1: flammable liquids

The trigger is more than 235 litres of flammable liquids located in a building or room, or flammable liquids dispensed in a building, room or area in any amount. The review addresses sections 22(1), (2) and (4). See the flammable liquids PSR page for the cabinet rules.

Item 2: machine safeguarding

Light curtains, area scanners, safety mats, two-hand controls, beam systems and interlocked barrier guards used as protective elements bring a machine into Item 2. Fixed guards, emergency stops and pull cords on their own don't. Robot cells, palletizers and presses are the usual cases; the machine guarding pre-start review page covers the detail. If the engineer needs evidence that the safety circuits are reliable enough, that's a performance level assessment of the safety functions, a separate piece of work.

Item 3: racks and stacking structures

Racks loaded by lift trucks are covered, whether steel, wood, aluminum or concrete. A new rack, a modification that changes the configuration, a change of lift truck type or loads beyond the design parameters can all trigger it. Read more on the racking pre-start review page.

Item 4: ignition and explosion hazards

Any process with a risk of ignition or explosion that creates an imminent hazard falls here, including dip tanks and ovens where that risk exists. The spray booth exemption covers the booth only, not robots or other equipment installed inside it. The ignition and explosion PSR page explains the scope, which runs to the whole process, piping included. Where flammable gas or vapour is present, electrical equipment selection usually depends on the zones shown on hazardous area classification drawings.

Item 5: dust collectors

A dust collector whose use involves a risk of ignition or explosion needs a dust collector review against section 65, and there's no exemption. Some collector types, such as those that use an inert liquid, are out of scope. Where a collector serves a process that already carries an ignition risk, the process-level ignition review usually runs alongside it.

Item 6: aluminum, steel and foundries

A factory that produces aluminum or steel, or a foundry that melts or handles molten material, needs a review of the physical set-up around the melting unit. There's no exemption. The foundry PSR page lists the sections involved.

Item 7: lifting devices

Travelling, overhead, monorail, gantry and jib cranes, other lifting devices supported by a structure, and vehicle lifts and hoists are covered. The review focuses on whether the supporting structure can carry the load, and Item 7 reports must include structural adequacy details. Forklifts, scissor lifts and mobile cranes are out of scope. More on the lifting device PSR page.

Item 8: hazardous substances and ventilation

A process that uses or produces a hazardous biological or chemical agent, and relies on ventilation to keep exposure within Reg. 833 limits, needs a review of that ventilation. Comfort heating and cooling isn't included. The ventilation PSR page covers hygiene testing and records.

Which section 7 item applies to my equipment?

A single project can touch several items. A new paint line might involve dispensing (Item 1), the booth and its oven (Item 4), a robot inside the booth (Item 2) and solvent exposure control (Item 8). Each applicable item is assessed, though one firm can usually cover them in one engagement. For budgeting, how much a pre-start review costs compares the items side by side.

When the fit isn't obvious, the do-I-need-a-PSR checker follows the ministry's own flow chart, one question at a time.

Who conducts the review

Section 7(4) requires an engineer for Items 1 to 7. Under the OHSA that means a person licensed as a professional engineer, or holding a limited licence, under the Professional Engineers Act. Engineers from other provinces need an Ontario licence. In-house engineers can do the work; a firm offering it to the public needs a certificate of authorization from Professional Engineers Ontario.

Item 8 can be reviewed by a professional engineer or another qualified person, such as a certified industrial hygienist. PreStartReview.ca is a referral service: we connect you with an independent Ontario engineering firm that conducts the review and signs the report.

The report and what happens before start-up

Under section 7(5), the report goes to the owner, lessee or employer in writing, signed and dated, and sealed under the Professional Engineers Act when an engineer did the review. It sets out the measures needed to comply with the applicable sections, or says clearly that none are needed. Item 3 and 7 reports add structural adequacy details, and any testing before start-up comes with the measures that protect workers during it.

Three rules follow. The equipment can't run until the measures are taken or the joint health and safety committee (or representative) has written notice of what was done. A copy of the report goes to the committee before start-up. The report and supporting documents stay readily accessible at the workplace for as long as the equipment does.

If an inspector finds equipment running without a required review, the likely result is a compliance order from the Ministry of Labour, and sometimes a requirement for an inspector-ordered engineer's report on the equipment as well.

Exemptions

The only exemptions are the ones written into Items 1, 2, 3, 4, 7 and 8 of the Table, plus logging operations. A CSA, ULC or CE mark doesn't exempt anything on its own (the page on European machinery with a CE mark explains why), and an exemption only counts if the documents proving it are on hand. The full list, item by item, is in the exemptions overview.

Questions people ask

What does Reg 851 section 7 require?

It requires the owner, lessee or employer of a factory to have a pre-start health and safety review done before a new or modified apparatus, structure, protective element or process is used, if one of the eight Table circumstances will exist. The review produces a written, signed report listing the measures needed to comply. The equipment can't be operated until the review is done and the measures are taken, or the joint health and safety committee has written notice of what was done.

What are Items 1 to 8 in the section 7 table?

Item 1 is flammable liquids, Item 2 machine safeguarding devices and interlocked guards, Item 3 racks and stacking structures, and Item 4 processes with a risk of ignition or explosion. Item 5 is dust collectors with an ignition or explosion risk, Item 6 aluminum or steel production and foundries, Item 7 cranes, other structure-supported lifting devices and vehicle lifts, and Item 8 ventilation used to control hazardous biological or chemical agents.

Who must conduct a section 7 review?

For Items 1 to 7, an engineer: someone licensed as a professional engineer, or holding a limited licence, under Ontario's Professional Engineers Act, who signs, dates and seals the report. For Item 8, a professional engineer or another qualified person, such as a certified industrial hygienist. A non-engineer reviewer must state their qualifications in the report, and an engineer licensed only in another province can't sign one.

What changed under O. Reg. 434/21?

O. Reg. 434/21 replaced section 7's trigger, report and record-keeping rules and the Table, and revoked the old subsections 10 to 15, effective January 1, 2022. The current version requires a copy of the report to go to the joint health and safety committee before start-up, and exemption documents to be kept at the workplace. A later amendment, O. Reg. 374/22, tied the word engineer to the OHSA definition.

Does section 7 apply outside factories?

No. Section 7 applies in a factory as the Occupational Health and Safety Act defines it, and it expressly doesn't apply at a logging operation. Warehouses that use machinery such as lift trucks, recycling facilities and transit maintenance shops can be factories under that definition.

Is a CSA or CE mark an exemption from section 7?

No. The ministry's guideline says marks and labels such as CSA, ULC or CE don't show compliance with Reg. 851, so a mark on its own never removes the need for a review. What can count is a document that names the specific standards the equipment was built and installed to, where those standards are on the guideline's list for that Table item.